Dept. of Trans. PROGRESS Serial No. Contract No. 22-234-16-00 07-291304 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 14% Location: Federal Project: 07-VEN-33-7.6/7.6 NONE Progress payment No. 005 Payment period ending: 08-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 406,406.20 49,980.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 119,315.02 119,315.02 4. Earned Subject to Retention 525,721.22 169,295.02 5. Mobilization 367,500.00 122,500.00 6. Total Work Completed 773,906.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 893,221.22 291,795.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 291,795.02