Dept. of Trans. PROGRESS Serial No. Contract No. 24-234-10-26 07-291404 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 32% Location: Federal Project: 07-LA-1-56.5/56.9 ACST-P001(674) Progress payment No. 039 Payment period ending: 08-20-24 STACY AND WITBECK INC 2800 HARBOR BAY PKWY ALAMEDA CA 94502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,034,175.31 334,600.00 2. a. Extra Work 3,382,688.43 203,265.15 b. Adustment Comp. 905,856.62 0.00 3. Materials on Hand 320,532.07 0.00 4. Earned Subject to Retention 11,643,252.43 537,865.15 5. Mobilization 1,070,000.00 0.00 6. Total Work Completed 12,392,720.36 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,713,252.43 537,865.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 537,865.15