Dept. of Trans. PROGRESS Serial No. Contract No. 25-022-12-24 07-291404 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 41% Location: Federal Project: 07-LA-1-56.5/56.9 ACST-P001(674) Progress payment No. 044 Payment period ending: 01-20-25 STACY AND WITBECK INC 2800 HARBOR BAY PKWY ALAMEDA CA 94502 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,926,937.45 -138,108.00 2. a. Extra Work 4,429,255.04 314,646.83 b. Adustment Comp. 905,856.62 0.00 3. Materials on Hand 245,107.07 0.00 4. Earned Subject to Retention 13,507,156.18 176,538.83 5. Mobilization 1,070,000.00 0.00 6. Total Work Completed 14,332,049.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,577,156.18 176,538.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 176,538.83