Dept. of Trans. PROGRESS Serial No. Contract No. 16-025-14-26 07-292204 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 1% Location: Federal Project: 07-LA-2-R17.8/R19.5 NHP-X037(181) Progress payment No. 001 Payment period ending: 01-20-16 DREAMBUILDER CONSTRUCTION CORP. 1324 E LAWSON LANE PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,500.00 22,500.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 22,500.00 22,500.00 5. Mobilization 6. Total Work Completed 22,500.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,500.00 22,500.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,500.00