Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-08-00 07-292204 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 29% Location: Federal Project: 07-LA-2-R17.8/R19.5 NHP-X037(181) Progress payment No. 008 Payment period ending: 08-20-16 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,112,587.18 226,018.47 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,112,587.18 226,018.47 5. Mobilization 174,463.70 0.00 6. Total Work Completed 1,287,050.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,287,050.88 226,018.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 226,018.47