Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-08-00 07-293404 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 24% Location: Federal Project: 07-LA-5-25.2/25.9 HSNH-PIG 005-3109-E Progress payment No. 002 Payment period ending: 08-20-16 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 273,124.08 248,680.08 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 273,124.08 248,680.08 5. Mobilization 187,500.00 187,500.00 6. Total Work Completed 460,624.08 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 450,624.08 426,180.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 426,180.08