Dept. of Trans. PROGRESS Serial No. Contract No. 22-202-09-53 07-293604 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 29% Location: Federal Project: 07-LA-405-14.3/15.8 ACIM-405-2(999) Progress payment No. 012 Payment period ending: 07-20-22 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,773,503.17 1,246,142.26 2. a. Extra Work 528,322.04 46,938.52 b. Adustment Comp. 3. Materials on Hand 993,079.45 -358,450.27 4. Earned Subject to Retention 13,294,904.66 934,630.51 5. Mobilization 3,895,000.00 0.00 6. Total Work Completed 16,196,825.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,189,904.66 934,630.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 934,630.51