Dept. of Trans. PROGRESS Serial No. Contract No. 23-205-12-06 07-293604 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 57% Location: Federal Project: 07-LA-405-14.3/15.8 ACIM-405-2(999) Progress payment No. 024 Payment period ending: 07-20-23 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 27,038,364.69 1,000,856.40 2. a. Extra Work 648,999.71 57,308.94 b. Adustment Comp. 276,155.51 180,792.80 3. Materials on Hand 934,483.00 -117,417.33 4. Earned Subject to Retention 28,898,002.91 1,121,540.81 5. Mobilization 4,100,000.00 0.00 6. Total Work Completed 32,063,519.91 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,988,002.91 1,121,540.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,121,540.81