Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-16-33 07-293604 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 67% Location: Federal Project: 07-LA-405-14.3/15.8 ACIM-405-2(999) Progress payment No. 028 Payment period ending: 11-20-23 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,928,791.38 1,349,476.75 2. a. Extra Work 816,741.94 27,844.80 b. Adustment Comp. 871,636.91 306,272.02 3. Materials on Hand 1,056,666.30 6,663.18 4. Earned Subject to Retention 33,673,836.53 1,690,256.75 5. Mobilization 4,100,000.00 0.00 6. Total Work Completed 36,717,170.23 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,763,836.53 1,690,256.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,690,256.75