Dept. of Trans. PROGRESS Serial No. Contract No. 24-081-09-42 07-293604 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 73% Location: Federal Project: 07-LA-405-14.3/15.8 ACIM-405-2(999) Progress payment No. 032 Payment period ending: 03-20-24 ORTIZ ENTERPRISES INC 6 CUSHING #200 IRVINE CA 926184221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,687,044.58 988,765.70 2. a. Extra Work 1,196,834.12 60,930.52 b. Adustment Comp. 965,901.43 0.00 3. Materials on Hand 340,387.72 -581,045.90 4. Earned Subject to Retention 36,190,167.85 468,650.32 5. Mobilization 4,100,000.00 0.00 6. Total Work Completed 39,949,780.13 7. Deductions -25,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,265,167.85 463,650.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 463,650.32