Dept. of Trans. PROGRESS Serial No. Contract No. 16-116-12-30 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 52% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 012 Payment period ending: 04-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,775,636.90 2,699,362.94 2. a. Extra Work b. Adustment Comp. 500,000.00 200,000.00 3. Materials on Hand 1,942,031.83 413,740.69 4. Earned Subject to Retention 14,217,668.73 3,313,103.63 5. Mobilization 4,180,271.23 0.00 6. Total Work Completed 16,455,908.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,397,939.96 3,313,103.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,313,103.63