Dept. of Trans. PROGRESS Serial No. Contract No. 16-333-15-24 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 83% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 020 Payment period ending: 11-20-16 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,519,388.28 1,409,917.36 2. a. Extra Work 419,170.14 22,681.65 b. Adustment Comp. 443,656.00 -1,208,491.28 3. Materials on Hand 896,398.07 12,994.06 4. Earned Subject to Retention 36,278,612.49 237,101.79 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 39,782,499.92 7. Deductions -31,400.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,647,497.99 232,101.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 232,101.79