Dept. of Trans. PROGRESS Serial No. Contract No. 17-024-09-49 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 83% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 022 Payment period ending: 01-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,192,552.12 176,950.88 2. a. Extra Work 432,980.01 13,809.87 b. Adustment Comp. 5,302.36 -87,488.93 3. Materials on Hand 1,289,823.00 -11,997.50 4. Earned Subject to Retention 36,920,657.49 91,274.32 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 40,031,119.99 7. Deductions -31,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,289,542.99 91,274.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 91,274.32