Dept. of Trans. PROGRESS Serial No. Contract No. 17-082-11-32 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 92% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 024 Payment period ending: 03-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,300,403.88 1,832,852.59 2. a. Extra Work 462,372.01 29,392.00 b. Adustment Comp. -621,559.87 -626,862.23 3. Materials on Hand 444,123.46 -811,562.24 4. Earned Subject to Retention 37,585,339.48 423,820.12 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 41,541,501.52 7. Deductions -31,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,954,224.98 423,820.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 423,820.12