Dept. of Trans. PROGRESS Serial No. Contract No. 17-143-16-31 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 85% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 027 Payment period ending: 05-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 39,441,356.40 1,462,672.26 2. a. Extra Work 497,491.59 20,574.40 b. Adustment Comp. -408,747.29 146,926.81 3. Materials on Hand 410,586.00 -386,178.78 4. Earned Subject to Retention 39,940,686.70 1,243,994.69 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 43,930,386.20 7. Deductions -26,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 44,314,572.20 1,243,994.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,243,994.69