Dept. of Trans. PROGRESS Serial No. Contract No. 17-207-13-38 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 96% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 029 Payment period ending: 07-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,989,762.54 3,979,940.58 2. a. Extra Work 932,055.39 255,890.30 b. Adustment Comp. -1,205,545.98 -506,434.29 3. Materials on Hand 4. Earned Subject to Retention 44,716,271.95 3,729,396.59 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 49,116,557.45 7. Deductions -34,400.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,082,157.45 3,721,396.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,721,396.59