Dept. of Trans. PROGRESS Serial No. Contract No. 17-233-18-22 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 030 Payment period ending: 08-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,685,055.96 695,293.42 2. a. Extra Work 1,929,511.83 997,456.44 b. Adustment Comp. -1,209,729.84 -4,183.86 3. Materials on Hand 4. Earned Subject to Retention 46,404,837.95 1,688,566.00 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 50,805,123.45 7. Deductions -218,223.00 -183,823.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 50,586,900.45 1,504,743.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,504,743.00