Dept. of Trans. PROGRESS Serial No. Contract No. 17-296-15-18 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 032 Payment period ending: 10-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,180,630.96 130,200.00 2. a. Extra Work 1,882,075.63 0.00 b. Adustment Comp. -1,209,729.84 0.00 3. Materials on Hand 4. Earned Subject to Retention 46,852,976.75 130,200.00 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 51,253,262.25 7. Deductions -54,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,198,862.25 130,200.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 130,200.00