Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-10-47 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 033 Payment period ending: 11-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,180,630.96 0.00 2. a. Extra Work 2,025,710.36 143,634.73 b. Adustment Comp. -1,209,729.84 0.00 3. Materials on Hand 4. Earned Subject to Retention 46,996,611.48 143,634.73 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 51,396,896.98 7. Deductions -44,400.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,352,496.98 153,634.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 153,634.73