Dept. of Trans. PROGRESS Serial No. Contract No. 18-082-16-51 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 036 Payment period ending: 03-20-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,420,425.81 0.00 2. a. Extra Work 2,241,602.55 173,956.00 b. Adustment Comp. -1,203,846.77 0.00 3. Materials on Hand 4. Earned Subject to Retention 47,458,181.59 173,956.00 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 51,858,467.09 7. Deductions -72,933.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,785,534.09 173,956.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,956.00