Dept. of Trans. PROGRESS Serial No. Contract No. 18-169-13-32 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 039 Payment period ending: 06-20-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,449,521.61 12,600.00 2. a. Extra Work 2,983,420.47 285,574.73 b. Adustment Comp. -1,172,729.24 5,278.33 3. Materials on Hand 4. Earned Subject to Retention 48,260,212.84 303,453.06 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 52,660,498.34 7. Deductions -72,933.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,587,565.34 303,453.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 303,453.06