Dept. of Trans. PROGRESS Serial No. Contract No. 18-267-11-54 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 041 Payment period ending: 09-20-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,441,846.61 -7,675.00 2. a. Extra Work 3,091,452.57 65,091.20 b. Adustment Comp. -1,172,729.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 48,360,569.94 57,416.20 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 52,760,855.44 7. Deductions -78,400.00 -40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,682,455.44 17,416.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,416.20