Dept. of Trans. PROGRESS Serial No. Contract No. 18-295-15-33 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 042 Payment period ending: 10-20-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,441,846.61 0.00 2. a. Extra Work 3,100,188.49 8,735.92 b. Adustment Comp. -1,172,729.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 48,369,305.86 8,735.92 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 52,769,591.36 7. Deductions -38,400.00 40,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,731,191.36 48,735.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,735.92