Dept. of Trans. PROGRESS Serial No. Contract No. 18-331-15-46 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 99% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 043 Payment period ending: 11-20-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,465,696.61 23,850.00 2. a. Extra Work 3,127,483.28 27,294.79 b. Adustment Comp. -1,172,729.24 0.00 3. Materials on Hand 4. Earned Subject to Retention 48,420,450.65 51,144.79 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 52,820,736.15 7. Deductions -38,400.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,782,336.15 51,144.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,144.79