Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-043-12-05 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 045 Payment period ending: 12-21-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,550,158.32 84,461.71 2. a. Extra Work 3,168,937.18 35,725.83 b. Adustment Comp. -914,374.41 258,354.83 3. Materials on Hand 4. Earned Subject to Retention 48,804,721.09 378,542.37 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 53,205,006.59 7. Deductions -58,400.00 -18,567.98 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,146,606.59 359,974.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 359,974.39