Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-052-15-40 07-294704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-101-11.8/35.3 NHP-Q101(247) Progress payment No. 046 Payment period ending: 12-21-18 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,576,592.77 26,434.45 2. a. Extra Work 3,226,517.89 57,580.71 b. Adustment Comp. -885,942.35 28,432.06 3. Materials on Hand 4. Earned Subject to Retention 48,917,168.31 112,447.22 5. Mobilization 4,400,285.50 0.00 6. Total Work Completed 53,317,453.81 7. Deductions -38,400.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,279,053.81 132,447.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 132,447.22