Dept. of Trans. PROGRESS Serial No. Contract No. 16-236-13-27 07-295704 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 77% Location: Federal Project: 07-LA-605-0.0/20.2 NHPI-605-2(967) Progress payment No. 021 Payment period ending: 08-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,238,236.36 1,018,717.84 2. a. Extra Work 619,956.54 35,965.68 b. Adustment Comp. 3. Materials on Hand 640,955.98 -296,381.68 4. Earned Subject to Retention 7,499,148.88 758,301.84 5. Mobilization 213,750.00 0.00 6. Total Work Completed 7,071,942.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,712,898.88 758,301.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 758,301.84