Dept. of Trans. PROGRESS Serial No. Contract No. 16-357-13-40 07-295704 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 86% Location: Federal Project: 07-LA-605-0.0/20.2 NHPI-605-2(967) Progress payment No. 025 Payment period ending: 12-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,275,371.62 926,991.12 2. a. Extra Work 655,274.24 4,840.32 b. Adustment Comp. 3. Materials on Hand 305,945.30 -503,722.73 4. Earned Subject to Retention 10,236,591.16 428,108.71 5. Mobilization 213,750.00 0.00 6. Total Work Completed 10,144,395.86 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,450,341.16 428,108.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 428,108.71