Dept. of Trans. PROGRESS Serial No. Contract No. 17-024-14-30 07-295704 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 87% Location: Federal Project: 07-LA-605-0.0/20.2 NHPI-605-2(967) Progress payment No. 026 Payment period ending: 01-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,555,653.26 280,281.64 2. a. Extra Work 655,274.24 0.00 b. Adustment Comp. 3. Materials on Hand 204,448.75 -101,496.55 4. Earned Subject to Retention 10,415,376.25 178,785.09 5. Mobilization 213,750.00 0.00 6. Total Work Completed 10,424,677.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,629,126.25 178,785.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 178,785.09