Dept. of Trans. PROGRESS Serial No. Contract No. 17-171-10-31 07-295704 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 92% Location: Federal Project: 07-LA-605-0.0/20.2 NHPI-605-2(967) Progress payment No. 031 Payment period ending: 06-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,683,150.10 1,333,122.58 2. a. Extra Work 681,606.29 0.00 b. Adustment Comp. 146,171.45 0.00 3. Materials on Hand 425,343.33 -568,088.60 4. Earned Subject to Retention 14,936,271.17 765,033.98 5. Mobilization 225,000.00 0.00 6. Total Work Completed 14,735,927.84 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,161,271.17 765,033.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 765,033.98