Dept. of Trans. PROGRESS Serial No. Contract No. 17-356-14-45 07-295704 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 99% Location: Federal Project: 07-LA-605-0.0/20.2 NHPI-605-2(967) Progress payment No. 037 Payment period ending: 12-20-17 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,863,808.09 354,279.20 2. a. Extra Work 706,448.81 0.00 b. Adustment Comp. 146,171.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 20,716,428.35 354,279.20 5. Mobilization 225,000.00 0.00 6. Total Work Completed 20,941,428.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,941,428.35 354,279.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 354,279.20