Dept. of Trans. PROGRESS Serial No. Contract No. 18-057-12-37 07-295704 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 100% Location: Federal Project: 07-LA-605-0.0/20.2 NHPI-605-2(967) Progress payment No. 039 Payment period ending: 02-20-18 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,105,525.49 165,505.00 2. a. Extra Work 798,757.09 80,941.41 b. Adustment Comp. 146,171.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 21,050,454.03 246,446.41 5. Mobilization 225,000.00 0.00 6. Total Work Completed 21,275,454.03 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,275,454.03 256,446.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 256,446.41