Dept. of Trans. PROGRESS Serial No. Contract No. 19-084-12-44 07-296104 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 17% Location: Federal Project: 07-LA-405-0.7/6.7 ACIM-405-2(995) Progress payment No. 005 Payment period ending: 03-20-19 DIVERSIFIED LANDSCAPE COMPANY 21730 BUNDY CANYON RD WILDOMAR CA 92595 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 585,857.70 158,964.90 2. a. Extra Work 20,857.86 809.48 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 606,715.56 159,774.38 5. Mobilization 56,810.00 0.00 6. Total Work Completed 663,525.56 7. Deductions -30,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 633,525.56 139,774.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,774.38