Dept. of Trans. PROGRESS Serial No. Contract No. 18-114-09-17 07-296204 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 17% Location: Federal Project: 07-LA-91-R11.8/R14.1 ACNH-P091-1(145) Progress payment No. 004 Payment period ending: 04-20-18 STL LANDSCAPE INC 8122 COMPTON AVE LOS ANGELES CA 90001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 376,591.00 204,021.00 2. a. Extra Work 807.54 807.54 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 377,398.54 204,828.54 5. Mobilization 33,250.00 7,000.00 6. Total Work Completed 410,648.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 410,648.54 211,828.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 211,828.54