Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-10-24 07-296404 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 65% Location: Federal Project: 07-LA-5-16.1/17.0 ACNH-X037(202) Progress payment No. 007 Payment period ending: 04-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,060,520.70 275,822.00 2. a. Extra Work 36,583.03 25,989.55 b. Adustment Comp. 3. Materials on Hand 0.00 -100,815.21 4. Earned Subject to Retention 1,097,103.73 200,996.34 5. Mobilization 94,050.00 19,800.00 6. Total Work Completed 1,191,153.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,191,153.73 220,796.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 220,796.34