Dept. of Trans. PROGRESS Serial No. Contract No. 19-295-11-48 07-296404 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 99% Location: Federal Project: 07-LA-5-16.1/17.0 ACNH-X037(202) Progress payment No. 013 Payment period ending: 10-20-19 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,726,155.65 594,227.55 2. a. Extra Work 222,019.91 1,711.78 b. Adustment Comp. 3. Materials on Hand 22,999.00 -19,554.00 4. Earned Subject to Retention 2,971,174.56 576,385.33 5. Mobilization 99,000.00 4,950.00 6. Total Work Completed 3,047,175.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,070,174.56 581,335.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 581,335.33