Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-225-15-54 07-296404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-16.1/17.0 ACNH-X037(202) Progress payment No. 019 Payment period ending: 04-15-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,210,792.75 384,748.50 2. a. Extra Work 327,011.15 18,812.97 b. Adustment Comp. -97,020.00 -97,020.00 3. Materials on Hand 4. Earned Subject to Retention 5,440,783.90 306,541.47 5. Mobilization 99,000.00 0.00 6. Total Work Completed 5,539,783.90 7. Deductions -15,000.00 -15,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,524,783.90 291,541.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 291,541.47