Dept. of Trans. PROGRESS Serial No. Contract No. 21-294-11-43 07-296604 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 77% Location: Federal Project: 07-LA-10-15.0/18.3 ACIM-010-1(840) Progress payment No. 036 Payment period ending: 10-20-21 CL COATINGS INC 26713 MADISON AVE MURRIETA CA 92562 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,265,458.58 473,025.82 2. a. Extra Work 21,050.00 0.00 b. Adustment Comp. 3. Materials on Hand 90,000.00 -10,000.00 4. Earned Subject to Retention 19,376,508.58 463,025.82 5. Mobilization 2,500,000.00 0.00 6. Total Work Completed 21,786,508.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,876,508.58 463,025.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 463,025.82