Dept. of Trans. PROGRESS Serial No. Contract No. 23-025-08-07 07-296604 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 99% Location: Federal Project: 07-LA-10-15.0/18.3 ACIM-010-1(840) Progress payment No. 047 Payment period ending: 01-20-23 SOCAL PACIFIC CONSTRUCTION CORP 26713 MADISON AVE MURRIETA CA 92562 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,895,868.77 738,657.19 2. a. Extra Work 114,290.00 93,240.00 b. Adustment Comp. 640,925.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 25,651,084.28 831,897.19 5. Mobilization 2,500,000.00 0.00 6. Total Work Completed 28,151,084.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,151,084.28 831,897.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 831,897.19