Dept. of Trans. PROGRESS Serial No. Contract No. 20-169-16-31 07-2975U4 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 63% Location: Federal Project: 07-LA-110-24.0/30.4 HNHG-P110(19) Progress payment No. 014 Payment period ending: 06-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,357,083.15 493,570.65 2. a. Extra Work 70,734.77 6,215.19 b. Adustment Comp. 3. Materials on Hand 86,600.38 -6,917.00 4. Earned Subject to Retention 1,514,418.30 492,868.84 5. Mobilization 313,500.00 66,000.00 6. Total Work Completed 1,741,317.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,827,918.30 558,868.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 558,868.84