Dept. of Trans. PROGRESS Serial No. Contract No. 20-205-15-40 07-2975U4 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 67% Location: Federal Project: 07-LA-110-24.0/30.4 HNHG-P110(19) Progress payment No. 015 Payment period ending: 07-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,847,144.35 490,061.20 2. a. Extra Work 79,101.82 8,367.05 b. Adustment Comp. 3. Materials on Hand 67,790.38 -18,810.00 4. Earned Subject to Retention 1,994,036.55 479,618.25 5. Mobilization 313,500.00 0.00 6. Total Work Completed 2,239,746.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,307,536.55 479,618.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 479,618.25