Dept. of Trans. PROGRESS Serial No. Contract No. 20-324-11-49 07-2975U4 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 83% Location: Federal Project: 07-LA-110-24.0/30.4 HNHG-P110(19) Progress payment No. 019 Payment period ending: 11-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,771,147.60 278,118.75 2. a. Extra Work 142,834.72 5,515.37 b. Adustment Comp. 3. Materials on Hand 63,889.38 -3,901.00 4. Earned Subject to Retention 2,977,871.70 279,733.12 5. Mobilization 313,500.00 0.00 6. Total Work Completed 3,227,482.32 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,291,371.70 279,733.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 279,733.12