Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-126-13-50 07-298604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-101-1.3/6.3 ACNH-Q101(323) Progress payment No. 010 Payment period ending: 03-12-19 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 776,066.50 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 776,066.50 0.00 5. Mobilization 92,000.00 0.00 6. Total Work Completed 868,066.50 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 868,066.50 1,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,000.00