Dept. of Trans. PROGRESS Serial No. Contract No. 20-143-12-35 07-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 100% Location: Federal Project: 07-LA-1-3.5/3.5 NONE Progress payment No. 004 Payment period ending: 05-20-20 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 369,231.80 11,194.00 2. a. Extra Work 10,476.27 10,476.27 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 379,708.07 21,670.27 5. Mobilization 45,000.00 0.00 6. Total Work Completed 424,708.07 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 424,708.07 21,670.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,670.27