Dept. of Trans. PROGRESS Serial No. Contract No. 20-357-16-11 07-299104 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 07-LA-1-3.5/3.5 NONE Progress payment No. 008 Payment period ending: 12-20-20 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 375,412.00 0.00 2. a. Extra Work 25,778.62 2,903.99 b. Adustment Comp. 30,216.58 0.00 3. Materials on Hand 4. Earned Subject to Retention 431,407.20 2,903.99 5. Mobilization 45,000.00 0.00 6. Total Work Completed 476,407.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 476,407.20 2,903.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,903.99