Dept. of Trans. PROGRESS Serial No. Contract No. 14-238-10-50 07-2W4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 100% 07-LA-0 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-14 TRAFFIC DEVELOPMENT SERVICES 207 W LOS ANGELES AVE #252 MOORPARK CA 93021 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,425.55 20,425.55 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 20,425.55 20,425.55 5. Mobilization 6. Total Work Completed 20,425.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,425.55 20,425.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,425.55