Dept. of Trans. PROGRESS Serial No. Contract No. 16-358-09-02 07-2W4704 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 07-LA-1-35.6/37.1 NONE Progress payment No. 010 Payment period ending: 12-20-16 DREAMBUILDER CONSTRUCTION CORP 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,089,805.00 12,750.00 2. a. Extra Work 240,560.14 113,159.84 b. Adustment Comp. 330,343.01 -22,211.84 3. Materials on Hand 4. Earned Subject to Retention 1,660,708.15 103,698.00 5. Mobilization 150,006.00 0.00 6. Total Work Completed 1,810,714.15 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,800,714.15 103,698.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 103,698.00