Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 16-349-11-34 07-2W6404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-10-20.2/23.6 NONE Progress payment No. 006 Payment period ending: 10-25-16 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 380,627.55 7,038.50 2. a. Extra Work 50,442.23 47,844.73 b. Adustment Comp. 1,386.21 0.00 3. Materials on Hand 4. Earned Subject to Retention 432,455.99 54,883.23 5. Mobilization 45,000.00 0.00 6. Total Work Completed 477,455.99 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 475,455.99 52,883.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,883.23