Dept. of Trans. PROGRESS Serial No. Contract No. 17-142-15-13 07-2W6604 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 93% Location: Federal Project: 07-LA-10-26.8/30.8 NHPI-101(832) Progress payment No. 002 Payment period ending: 05-20-17 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 110,030.80 76,205.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 110,030.80 76,205.00 5. Mobilization 63,750.00 63,750.00 6. Total Work Completed 173,780.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 173,780.80 139,955.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,955.00