Dept. of Trans. PROGRESS Serial No. Contract No. 16-082-14-01 07-2W6904 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 21% Location: Federal Project: 07-LA-5-13.8/28.2 NONE Progress payment No. 002 Payment period ending: 03-20-16 AUTOBAHN CONSTRUCTION, INC 933 N. BATAVIA ST ORANGE CA 92867 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 163,105.95 98,755.15 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 163,105.95 98,755.15 5. Mobilization 66,500.00 31,500.00 6. Total Work Completed 229,605.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 229,605.95 130,255.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 130,255.15